We have been informed that pile driving will continue for the next 2 Saturdays. (2-18, 2-25). Monday the 20th they will be working as the union does not get the holiday off. They will be moving the crane as far from the building as they can to help with the vibration and sound issues.
As of 2:00pm on Friday the 17th they have drove 138 piles of the 455 that needs to be driven.
Monday they were able to drive 20 piles, Tuesday they drove 24 piles and Wednesday the drove 21 piles. This was done to try to catch up on some of the days that the crane had mechanical problems. The goal is to drive 10 to 12 piles a day.